Your Project Is Behind Schedule. Now What?

Featured on this episode:

  • Grab Your Free Script Guide here
  • Access the full video interview with Elana Steele of Steele Appliance here

What you will learn from this episode:

  • How to determine whether a construction delay actually affects the completion date
  • How to communicate delays and uncertainty without losing your client’s trust
  • How to protect your fees and capacity when projects run longer than expected

I’m currently working on a beautiful renovation and addition to a historic home. It’s a significant project with an experienced architect, wonderful homeowners, and a team that’s doing everything it can to move the work forward.

And we’re almost seven months behind where we expected to be.

The property is on a historic register, so we knew there would be additional requirements. What we didn’t anticipate was just how many layers of review we’d encounter. There were zoning issues, permitting challenges, conserved land considerations, and multiple historic review processes.

It wasn’t one big event that threw the schedule off. It happened gradually. We’d clear one hurdle, think we were finally moving forward, and then another would appear.

A few weeks here. Another review cycle there. Before we knew it, those delays had added up to months.

Here’s what I want you to understand about this project, though. The homeowners have been incredibly patient, and I don’t believe that’s an accident.

They’ve known what’s happening throughout the process. Nobody has been hiding the reality from them, and they’ve never been left wondering why things aren’t moving forward.

That’s an important distinction when we’re talking about how to handle construction delays.

Because a delay is one thing. How you manage it, communicate it, and understand its impact is something else entirely.

Not Every Construction Delay Means Your Project Is Behind Schedule

This is something I really want designers to understand.

An activity can be late without changing the project’s completion date.

Construction happens in a sequence, but not every task depends on every other task. Some activities can happen independently, while others must be completed before the next phase can begin.

Let’s say the tile for a powder room arrives three weeks late. If that room isn’t holding up other critical work, the delay may simply change when the tile gets installed.

That’s very different from a delay that affects everything scheduled to happen afterward.

So before you call your client with a revised completion date, you need to understand what has actually changed.

Which activity is delayed? What work depends on it? Can the contractor move something else forward while you’re waiting? And does any of this affect the overall completion date?

If your contractor tells you, “We’re a little behind,” that isn’t enough information.

Neither is, “We’ll catch up.”

Those statements should be the beginning of the conversation, not the end.

Get the Information You Need, Even When It’s Uncomfortable

I want to talk about something that happens on job sites, particularly when you’re working with experienced contractors and trades.

Sometimes you notice something that doesn’t look quite right, but you hesitate to say anything.

I’ve been there. You don’t want to question someone in front of the entire team, especially when your client is standing beside you. And you certainly don’t want to raise an issue only to discover you’ve misunderstood what’s happening.

But you still need answers.

What I’ve learned is that you don’t have to address every concern in the middle of a meeting. Sometimes the better approach is to wait until everyone leaves and pull the contractor aside. You can ask a direct question without making it accusatory.

Maybe you’ve misunderstood something. Maybe there’s a perfectly reasonable explanation. Or perhaps you’ve identified an issue that needs attention. The point is to have the conversation.

You’re managing more than a construction schedule. You’re managing relationships, personalities, expectations, and the information your client needs to make decisions.

And you cannot do that effectively if you’re afraid to ask questions.

Communicate the Delay Before Your Client Has to Ask

One of the most important things I do on my projects is maintain a regular rhythm of communication.

I send Friday updates to my clients, and I make sure the contractor understands that expectation from the beginning.

That means I’m going to communicate what’s happening on the project every week, whether the news is good, bad, or simply that we’re still waiting.

I actually love sending an update that says there’s nothing new to report. Sometimes that’s the best news because everything is progressing as expected.

But when we’re waiting three weeks for a review board meeting, I tell the client that too.

Think about my historic renovation project. If we’d said very little for months and then suddenly announced we were six or seven months behind, can you imagine that conversation?

The homeowners would have every reason to be furious.

Instead, they’ve been part of the conversation all along. They understand which hurdles we’ve encountered, what we’re doing about them, and what happens next.

They’re not happy about the delay, of course. Who would be? But they’re not left feeling abandoned or wondering whether anyone is paying attention.

When you’re managing construction delays, consistent communication is one of the most valuable things you can give your client.

Don’t Promise a Completion Date You Can’t Confirm

I understand the temptation to reassure a frustrated client.

They want to know when the project will be finished, and you want to give them an answer. But there is absolutely no upside to offering a date you cannot support. If that date comes and goes, you’ve made an already difficult situation worse.

When a client presses me for a completion date I can’t confirm, I tell them exactly that. Then I explain what we know, what’s been completed, what remains unresolved, and what we’re doing to get reliable information.

I also tell them when they’ll hear from me again.

Sometimes the contractor can provide a realistic date range rather than a specific completion date. That can be useful, as long as everyone understands what it represents.

And if your client has a hard deadline, that needs to be part of the conversation from the very beginning.

Maybe their lease is ending. Perhaps they’ve already sold their home, or they have family arriving for the holidays.

Those deadlines don’t magically move because construction falls behind.

If one is at risk, your client needs to know while there’s still time to make another plan.

That may be an uncomfortable conversation, but it’s also part of the expertise they’re paying you for.

Construction Delays Affect Your Business, Too

We spend a lot of time talking about what delays mean for the homeowner and contractor. But there’s another side to this that designers need to consider.

What does an extended construction schedule cost your business?

I structure my fees as flat fees based on the contractor’s estimated timeline. If a project is expected to take 12 months, that’s the information I use to calculate my fee.

I build in a contingency because I know construction schedules shift.

An additional two or three weeks may be something I’ve already accounted for. But when a project extends significantly beyond the original timeline, that’s a different situation.

If the extension is outside our control and requires additional work, it may be appropriate to address that through a fee addendum.

The explanation is straightforward. The original fee was based on a good-faith schedule estimate, and the project now requires more time.

But additional compensation doesn’t solve every problem.

Remember that historic project I mentioned? I expected it to be much further along by now. Instead, it’s overlapping with two other projects that were scheduled to begin around this time.

That creates a very real capacity problem.

The delay affects my calendar, my energy, and my ability to give every client the attention they deserve. And that’s something a fee addendum cannot fix.

When you evaluate the cost of a construction delay, remember that the financial impact is only part of the picture.

A New Completion Date Isn’t a Recovery Plan

If you’re dealing with a delayed project right now, I want you to start by getting clear answers.

What is actually delayed? Why did it happen? What other work is affected? What needs to happen next, and who is responsible for making that happen?

You also want to know whether something else can move forward while the team works through the issue.

And ideally, you’ve built the kind of relationship with your contractor where this information comes to you before you even have to ask.

I want the people on my projects to feel comfortable calling me when something goes wrong. I’d much rather work through a problem together than discover it after everyone has spent weeks avoiding the conversation.

Once you understand what’s happening, tell your client what you know.

Not what you hope will happen. Not a date someone threw out to make everyone feel better.

Tell them what’s confirmed, what’s still being worked out, what their options may be, and when they can expect another update.

You don’t have to offer certainty when you don’t have it. In fact, you shouldn’t.

But you do need to offer clarity.

Because simply handing a client a new completion date doesn’t explain how the team plans to get there.

Understanding the cause of the delay, its actual impact, and the steps needed to move forward is what turns a difficult situation into something you can manage.

And that’s ultimately what our clients are relying on us to do.


Like this Episode?

Be sure to check out Episode #294: The One Hour a Week That Keeps a Construction Project From Falling Apart

Be sure to check out Episode #287: What Interior Designers Get Wrong About the People Who Build Their Projects

Be sure to check out Episode #266: The 5 Construction Conversations That Prevent Chaos on Projects

follow the podcast

want to be a guest?

Fill out the form on the inquiry page under the podcast tab and we'll get in touch with you!

leave us a review!

We love hearing from you about your thoughts on the podcast, you can leave a review on apple!

You can find us anywhere! Click the icons to find us on the podcast platform you use!